| Assessment Year | 1997 |
|---|---|
| Principal Product | Corrugated Containers |
| NAICS |
n/a
|
| SIC | 2655: Fiber Cans, Tubes, Drums, and Similar Products |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
125,000
ft2
|
| Annual Production | 75,000,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $206,532 | 4,284,877 |
kWh
|
$0.048 |
| Electricity Demand | $39,605 | 10,290 |
kW-mo/yr
|
$3.85 |
| Fuel Oil #4 | $114,815 | 28,443 |
MMBtu
|
$4.04 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $937,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7145: Install skylights | $3,663 | $2,400 |
$3,663
89,390
kWh
|
- | - | - | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,225 | $1,311 |
$1,137
27,843
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,870 | $1,050 |
$3,870
84,115
kWh
|
- | - | - | - | - | - | |
| 04 | 2.2135: Repair and eliminate steam leaks | $2,570 | $625 | - | - |
$2,570
-
MMBtu
|
- | - | - | - | |
| 05 | 3.5316: Contract a wood pallet recycling company | $3,600 | - | - | - | - |
$3,600
-
lb
|
- | - | - | |
| 06 | 3.6192: Use a less expensive method of waste removal | $1,320 | - | - | - | - | - | - | $1,320 | - | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $921,346 | $1,400,000 | - | - | - | - | $(-1,578,654.0) | - | $2,500,000 | |
| TOTAL RECOMMENDED | $937,594 | $1,405,386 |
$8,670
201,348
kWh
|
$88
-
kW-mo/yr
|
$2,570
-
MMBtu
|
$3,600
-
lb
|
$(-1,578,654.0) | $1,320 | $2,500,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs