| Assessment Year | 1996 |
|---|---|
| Principal Product | Filtration and Purification Devices |
| NAICS |
n/a
|
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
160,000
ft2
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $354,606 | 7,387,163 |
kWh
|
$0.048 |
| Electricity Demand | $144,224 | 21,504 |
kW-mo/yr
|
$6.71 |
| LPG | $1,809 | 251 |
MMBtu
|
$7.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $145,056 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,832 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $97,999 | $5,544 |
$81,573
1,773,154
kWh
|
$16,426
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,368 | $16,471 |
$12,130
263,775
kWh
|
$2,238
-
kW-mo/yr
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $2,265 | $3,303 |
$1,822
38,101
kWh
|
$443
-
kW-mo/yr
|
- | |
| 04 | 2.1211: Move boiler to more efficient location | $10,185 | - |
$10,185
255,862
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,142 | $600 |
$8,142
119,871
kWh
|
- | - | |
| 06 | 2.7229: Air condition only space necessary | $8,857 | $880 | - |
$8,857
-
kW-mo/yr
|
- | |
| 07 | 3.5316: Contract a wood pallet recycling company | $3,240 | - | - | - | $3,240 | |
| TOTAL RECOMMENDED | $145,056 | $26,798 |
$113,852
2,450,763
kWh
|
$27,964
-
kW-mo/yr
|
$3,240 | ||
| TOTAL IMPLEMENTED | $23,832 | $3,903 |
$20,149
413,834
kWh
|
$443
-
kW-mo/yr
|
$3,240 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs