ITAC Assessment: UF0162
ITAC logo
ITAC Assessment: UF0162
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Fresh Chicken Eggs
NAICS
n/a
SIC 2015: Poultry Slaughtering and Processing
Sales Range $5
M
to 10
M
# of Employees 34
Plant Area 219,000
ft2
Annual Production 14,500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,407 2,067,702
kWh
Electricity Demand $33,851 5,042
kW-mo/yr
LPG $5,688 786
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,959 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,243

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $853 - $679
14,068
kWh
$174
-
kW-mo/yr
-
02 2.7122: Disconnect ballasts $1,934 $655 $1,744
15,533
kWh
$190
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $982 $576 $982
20,516
kWh
- -
04 2.4133: Use most efficient type of electric motors $7,309 $9,372 $6,097
126,905
kWh
$1,212
-
kW-mo/yr
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,167 $4,200 $1,167
24,326
kWh
- -
06 2.2622: Replace existing chiller with high efficiency model $2,640 $3,500 $2,213
46,014
kWh
$427
-
kW-mo/yr
-
07 3.8136: Switch to a solvent that can be cleaned and re-used $1,074 - - - $1,074
-
gal
TOTAL RECOMMENDED $15,959 $18,303 $12,882
247,362
kWh
$2,003
-
kW-mo/yr
$1,074
-
gal
TOTAL IMPLEMENTED $9,243 $10,027 $7,841
142,438
kWh
$1,402
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs