Assessment Year | 1996 |
---|---|
Principal Product | Fresh Chicken Eggs |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $5 M to 10M |
# of Employees | 34 |
Plant Area |
219,000
ft2
|
Annual Production | 14,500,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,407 | 2,067,702 |
kWh
|
$0.048 |
Electricity Demand | $33,851 | 5,042 |
kW-mo/yr
|
$6.71 |
LPG | $5,688 | 786 |
MMBtu
|
$7.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,959 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,243 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $853 | - |
$679
14,068
kWh
|
$174
-
kW-mo/yr
|
- | |
02 | 2.7122: Disconnect ballasts | $1,934 | $655 |
$1,744
15,533
kWh
|
$190
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $982 | $576 |
$982
20,516
kWh
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $7,309 | $9,372 |
$6,097
126,905
kWh
|
$1,212
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,167 | $4,200 |
$1,167
24,326
kWh
|
- | - | |
06 | 2.2622: Replace existing chiller with high efficiency model | $2,640 | $3,500 |
$2,213
46,014
kWh
|
$427
-
kW-mo/yr
|
- | |
07 | 3.8136: Switch to a solvent that can be cleaned and re-used | $1,074 | - | - | - |
$1,074
-
gal
|
|
TOTAL RECOMMENDED | $15,959 | $18,303 |
$12,882
247,362
kWh
|
$2,003
-
kW-mo/yr
|
$1,074
-
gal
|
||
TOTAL IMPLEMENTED | $9,243 | $10,027 |
$7,841
142,438
kWh
|
$1,402
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs