| Assessment Year | 2024 |
|---|---|
| Principal Product | Specialty Chemicals |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 105 |
| Plant Area |
56,200
ft2
|
| Annual Production | 37,000,000
lb
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,649 | 1,014,425 |
kWh
|
$0.11 |
| Electricity Demand | $55,933 | 4,792 |
kW-mo/yr
|
$11.67 |
| Natural Gas | $55,871 | 2,585 |
MMBtu
|
$21.61 |
| TOTAL YEARLY COSTS | $227,453 | |||
| RECOMMENDED SAVINGS* | $142,847 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,783 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $3,502 | - |
$3,502
30,721
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $942 | - |
$1,620
14,208
kWh
|
- | - | $(-678.0) | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,560 | $254 |
$1,368
12,001
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $6,353 | $4,013 | - | - |
$6,353
-
MMBtu
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $2,585 | $8,372 |
$1,659
14,522
kWh
|
- | - | $151 | $775 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,343 | $22,807 |
$4,326
37,951
kWh
|
$2,380
-
kW-mo/yr
|
- | $73 | $(-436.0) | |
| 07 | 2.9114: Use solar heat to make electricty | $121,562 | $882,352 |
$121,562
1,014,425
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $142,847 | $917,798 |
$134,037
1,123,828
kWh
|
$2,572
-
kW-mo/yr
|
$6,353
-
MMBtu
|
$(-454.0) | $339 | ||
| TOTAL IMPLEMENTED | $17,783 | $35,446 |
$8,973
78,682
kWh
|
$2,572
-
kW-mo/yr
|
$6,353
-
MMBtu
|
$(-454.0) | $339 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs