ITAC Assessment: UF0119
ITAC logo
ITAC Assessment: UF0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Circuit Boards
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 256,000
ft2
Annual Production 250
pieces
Production Hrs. Annual 2,300
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $517,456 8,357,562
kWh
Natural Gas $6,304 3,089
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $76,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,705

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,375 $3,338 $2,375
35,170
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $29,924 $84,732 $29,924
415,592
kWh
03 2.4133: Use most efficient type of electric motors $1,579 $1,457 $1,579
26,377
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,827 $350 $18,827
289,566
kWh
05 2.7492: Use proper thickness of insulation on building envelope $20,739 $18,879 $20,739
313,599
kWh
06 2.7135: Install occupancy sensors $3,078 $2,752 $3,078
44,549
kWh
TOTAL RECOMMENDED $76,522 $111,508 $76,522
1,124,853
kWh
TOTAL IMPLEMENTED $52,705 $89,877 $52,705
766,705
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs