Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Aluminum lids
NAICS
n/a
SIC 3411: Metal Cans
Sales Range $50
M
to 100
M
# of Employees 210
Plant Area 70,000
ft2
Annual Production 8,200,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,018,005 15,916,765
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,414 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,563

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,787 $7,746 $6,787
108,734
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,893 $1,150 $1,893
30,481
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $13,407 $14,664 $13,407
214,830
kWh
04 2.7135: Install occupancy sensors $2,210 $640 $2,210
39,566
kWh
05 2.4133: Use most efficient type of electric motors $29,665 $30,154 $29,665
468,933
kWh
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,316 $1,500 $6,316
112,837
kWh
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $33,584 $50,400 $33,584
599,648
kWh
08 2.7232: Replace existing hvac unit with high efficiency model $208 $950 $208
3,810
kWh
09 2.7142: Utilize higher efficiency lamps and/or ballasts $374 $520 $374
3,810
kWh
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,129 $3,000 $10,129
180,832
kWh
11 2.3212: Optimize plant power factor $2,841 $12,951 $2,841
-
kWh
TOTAL RECOMMENDED $107,414 $123,675 $107,414
1,763,481
kWh
TOTAL IMPLEMENTED $71,563 $71,605 $71,563
1,129,542
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs