Assessment Year | 1995 |
---|---|
Principal Product | Processed Chicken |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
100,000
ft2
|
Annual Production | 115,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $952,635 | 14,554,221 |
kWh
|
$0.065 |
Natural Gas | $202,716 | 32,986 |
MMBtu
|
$6.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $224,172 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,108 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,268 | $2,638 |
$7,268
135,991
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $7,054 | $17,625 |
$7,054
111,665
kWh
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,861 | $1,000 | - |
$8,861
-
MMBtu
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $5,255 | $5,200 | - |
$5,255
-
MMBtu
|
- | |
05 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $189,560 | $950,000 |
$361,151
6,520,809
kWh
|
$(-185,099.0)
-
MMBtu
|
$13,508 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $925 | $1,425 |
$925
23,154
kWh
|
- | - | |
07 | 2.1212: Operate boilers on high fire setting | $5,249 | - | - |
$5,249
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $224,172 | $977,888 |
$376,398
6,791,619
kWh
|
$(-165,734.0)
-
MMBtu
|
$13,508 | ||
TOTAL IMPLEMENTED | $24,108 | $22,688 |
$15,247
270,810
kWh
|
$8,861
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs