ITAC Assessment: UF0106
ITAC logo
ITAC Assessment: UF0106
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Processed Chicken
NAICS
n/a
SIC 2015: Poultry Slaughtering and Processing
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 100,000
ft2
Annual Production 115,000,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $952,635 14,554,221
kWh
Natural Gas $202,716 32,986
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $224,172 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,108

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,268 $2,638 $7,268
135,991
kWh
- -
02 2.4133: Use most efficient type of electric motors $7,054 $17,625 $7,054
111,665
kWh
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $8,861 $1,000 - $8,861
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $5,255 $5,200 - $5,255
-
MMBtu
-
05 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $189,560 $950,000 $361,151
6,520,809
kWh
$(-185,099.0)
-
MMBtu
$13,508
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $925 $1,425 $925
23,154
kWh
- -
07 2.1212: Operate boilers on high fire setting $5,249 - - $5,249
-
MMBtu
-
TOTAL RECOMMENDED $224,172 $977,888 $376,398
6,791,619
kWh
$(-165,734.0)
-
MMBtu
$13,508
TOTAL IMPLEMENTED $24,108 $22,688 $15,247
270,810
kWh
$8,861
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs