ITAC Assessment: UF0089
ITAC logo
ITAC Assessment: UF0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product steel fabricated products
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $5
M
to 10
M
# of Employees 87
Plant Area 76,000
ft2
Annual Production 5,000
ton
Production Hrs. Annual 5,616
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,188 860,492
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,331 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,347 $2,246 $5,347
75,322
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,449 $1,820 $1,449
27,257
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $534 $1,126 $534
7,620
kWh
04 2.7135: Install occupancy sensors $1,191 $320 $1,191
21,395
kWh
05 2.7232: Replace existing hvac unit with high efficiency model $2,372 $1,940 $2,372
35,463
kWh
06 2.4133: Use most efficient type of electric motors $3,008 $1,960 $3,008
42,497
kWh
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,430 $750 $1,430
20,223
kWh
TOTAL RECOMMENDED $15,331 $10,162 $15,331
229,777
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs