ITAC Assessment: UF0082
ITAC logo
ITAC Assessment: UF0082
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Cardboard Boxes
NAICS
n/a
SIC 2675: Die-Cut Paper and Paperboard and Cardboard
Sales Range $500
k
to 1
M
# of Employees 22
Plant Area 12,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,500
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,632 210,141
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,272 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,957

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $907 $1,527 $907
12,309
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $917 $2,370 $917
11,723
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $308 $100 $308
3,810
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,183 $2,250 $1,183
14,947
kWh
-
05 2.2136: Install / repair insulation on steam lines $1,957 $542 - $1,957
-
MMBtu
TOTAL RECOMMENDED $5,272 $6,789 $3,315
42,789
kWh
$1,957
-
MMBtu
TOTAL IMPLEMENTED $1,957 $542 - $1,957
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs