ITAC Assessment: UF0062
ITAC logo
ITAC Assessment: UF0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Frozen OJ Concentrate
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 629,877
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $874,322 23,173,213
kWh
Natural Gas $786,129 256,232
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $724,268 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,706

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,644 $3,350 $6,644
-
kWh
-
02 2.4133: Use most efficient type of electric motors $48,297 $41,915 $48,297
-
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $1,394 - - $1,394
-
MMBtu
04 2.2135: Repair and eliminate steam leaks $2,765 $1,200 - $2,765
-
MMBtu
05 2.4322: Use or replace with energy efficient substitutes $665,168 $3,843,600 - $665,168
-
MMBtu
TOTAL RECOMMENDED $724,268 $3,890,065 $54,941
-
kWh
$669,327
-
MMBtu
TOTAL IMPLEMENTED $57,706 $46,465 $54,941
-
kWh
$2,765
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs