ITAC Assessment: UF0058
ITAC logo
ITAC Assessment: UF0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Frozen Foods
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 63,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,029 2,058,617
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,270 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,572

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,572 $1,475 $3,572
71,512
kWh
02 2.7144: Install spectral reflectors / delamp $5,100 $8,400 $5,100
90,856
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $652 $1,482 $652
12,896
kWh
04 2.7232: Replace existing hvac unit with high efficiency model $390 $590 $390
7,913
kWh
05 2.2622: Replace existing chiller with high efficiency model $17,336 $63,000 $17,336
346,717
kWh
06 2.4231: Reduce the pressure of compressed air to the minimum required $14,220 $30,000 $14,220
284,291
kWh
TOTAL RECOMMENDED $41,270 $104,947 $41,270
814,185
kWh
TOTAL IMPLEMENTED $3,572 $1,475 $3,572
71,512
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs