ITAC Assessment: UF0057
ITAC logo
ITAC Assessment: UF0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Scientific lasers
NAICS
n/a
SIC 3845: Electromedical and Electrotherapeutic Apparatus
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 44,000
ft2
Annual Production 300
pieces
Production Hrs. Annual 7,865
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,089 1,002,638
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,077 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,909 $1,164 $2,909
48,359
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,283 $5,896 $1,283
21,395
kWh
03 2.7144: Install spectral reflectors / delamp $9,216 $33,045 $9,216
137,456
kWh
04 2.7111: Reduce illumination to minimum necessary levels $768 - $768
12,896
kWh
05 2.7135: Install occupancy sensors $192 $128 $192
3,224
kWh
06 2.4133: Use most efficient type of electric motors $53 $293 $53
879
kWh
07 2.7232: Replace existing hvac unit with high efficiency model $3,656 $4,000 $3,656
60,961
kWh
TOTAL RECOMMENDED $18,077 $44,526 $18,077
285,170
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs