ITAC Assessment: UF0028
ITAC logo
ITAC Assessment: UF0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PRE-STRESSED CONCRETE
NAICS
n/a
SIC 3449: Miscellaneous Structural Metal Work
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area
n/a
Annual Production 20,000
ton
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,086,952 17,549,238
kWh
LPG $23,435 3,774
MMBtu
Other Energy $3,187 503
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,866 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,866

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $864 $2,517 $864
14,068
kWh
02 2.7144: Install spectral reflectors / delamp $6,437 $2,400 $6,437
103,751
kWh
03 2.7233: Use properly designed and sized hvac equipment $1,125 $1,660 $1,125
18,171
kWh
04 2.4133: Use most efficient type of electric motors $5,440 $36,148 $5,440
87,632
kWh
TOTAL RECOMMENDED $13,866 $42,725 $13,866
223,622
kWh
TOTAL IMPLEMENTED $13,866 $42,725 $13,866
223,622
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs