Assessment Year | 1992 |
---|---|
Principal Product | PRE-STRESSED CONCRETE |
NAICS |
n/a
|
SIC | 3449: Miscellaneous Structural Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
n/a
|
Annual Production | 20,000
ton
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,086,952 | 17,549,238 |
kWh
|
$0.062 |
LPG | $23,435 | 3,774 |
MMBtu
|
$6.21 |
Other Energy | $3,187 | 503 |
MMBtu
|
$6.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,866 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $864 | $2,517 |
$864
14,068
kWh
|
|
02 | 2.7144: Install spectral reflectors / delamp | $6,437 | $2,400 |
$6,437
103,751
kWh
|
|
03 | 2.7233: Use properly designed and sized hvac equipment | $1,125 | $1,660 |
$1,125
18,171
kWh
|
|
04 | 2.4133: Use most efficient type of electric motors | $5,440 | $36,148 |
$5,440
87,632
kWh
|
|
TOTAL RECOMMENDED | $13,866 | $42,725 |
$13,866
223,622
kWh
|
||
TOTAL IMPLEMENTED | $13,866 | $42,725 |
$13,866
223,622
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs