ITAC Assessment: UF0015
ITAC logo
ITAC Assessment: UF0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product VENEER BOARDS/WOOD CHIPS
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $1
M
to 5
M
# of Employees 68
Plant Area
n/a
Annual Production 4,000
thousand feet
Production Hrs. Annual 7,200
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,003 601,114
kWh
Fuel Oil #6 $84,832 23,587
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,322 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $2,858 $3,000 - $2,858
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $220 - $220
2,931
kWh
-
03 2.4133: Use most efficient type of electric motors $280 $281 $280
3,810
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $869 - $869
12,016
kWh
-
05 2.7233: Use properly designed and sized hvac equipment $95 $200 $95
1,465
kWh
-
TOTAL RECOMMENDED $4,322 $3,481 $1,464
20,222
kWh
$2,858
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs