Assessment Year | 1991 |
---|---|
Principal Product | WIRE, BASKETS, SHELVING |
NAICS |
n/a
|
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $50 M to 100M |
# of Employees | 430 |
Plant Area |
n/a
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $447,192 | 7,072,099 |
kWh
|
$0.063 |
Natural Gas | $264,603 | 69,386 |
MMBtu
|
$3.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $89,904 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $27,648 | $34,850 |
$27,648
-
kWh
|
- | |
02 | 2.3511: Use plant owned transformers or lease transformers | $18,637 | $34,000 |
$18,637
-
kWh
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,117 | - |
$3,117
-
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,964 | - |
$13,964
221,278
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,775 | $21,477 |
$8,775
139,215
kWh
|
- | |
06 | 2.7123: Keep lamps and reflectors clean | $6,364 | - |
$6,364
101,700
kWh
|
- | |
07 | 2.4133: Use most efficient type of electric motors | $2,089 | $1,892 |
$2,089
33,118
kWh
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,841 | $3,067 |
$2,841
45,135
kWh
|
- | |
09 | 2.7233: Use properly designed and sized hvac equipment | $756 | $880 |
$756
12,016
kWh
|
- | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $5,713 | $20,700 | - |
$5,713
-
MMBtu
|
|
TOTAL RECOMMENDED | $89,904 | $116,866 |
$84,191
552,462
kWh
|
$5,713
-
MMBtu
|
||
TOTAL IMPLEMENTED | $89,904 | $116,866 |
$84,191
552,462
kWh
|
$5,713
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs