ITAC Assessment: UF0009
ITAC logo
ITAC Assessment: UF0009
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product MOBILE HOMES
NAICS
n/a
SIC 2451: Mobile Homes
Sales Range $10
M
to 50
M
# of Employees 335
Plant Area
n/a
Annual Production 1,506
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,362 800,996
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,525 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $696 $422 $696
8,206
kWh
02 2.7144: Install spectral reflectors / delamp $7,324 $7,430 $7,324
80,305
kWh
03 2.7233: Use properly designed and sized hvac equipment $1,422 $1,320 $1,422
18,171
kWh
04 2.4133: Use most efficient type of electric motors $119 $233 $119
1,465
kWh
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,964 - $1,964
-
kWh
TOTAL RECOMMENDED $11,525 $9,405 $11,525
108,147
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs