ITAC Assessment: UD1152
ITAC logo
ITAC Assessment: UD1152
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product religious worship/community service
NAICS 813110: Religious Organizations
SIC 8661: Religious Organizations
Sales Range less than $500
k
# of Employees 20
Plant Area 92,400
ft2
Annual Production 1
units
Production Hrs. Annual 2,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $181,290 1,294,400
kWh
Natural Gas $40,002 4,080
MMBtu
Waste Disposal Costs
Water Usage $15,100 1,000
Tgal
TOTAL YEARLY COSTS $236,392
RECOMMENDED SAVINGS* $163,942 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $19,384 $54,000 $19,384
138,399
kWh
-
02 2.7226: Use computer programs to optimize hvac performance $10,914 $18,000 $5,309
37,907
kWh
$5,605
-
MMBtu
03 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $5,847 $22,000 $3,231
23,072
kWh
$2,616
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $16,153 $24,000 $16,153
115,332
kWh
-
05 2.9114: Use solar heat to make electricty $111,644 $900,000 $111,644
797,130
kWh
-
TOTAL RECOMMENDED $163,942 $1,018,000 $155,721
1,111,840
kWh
$8,221
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs