| Assessment Year | 2026 |
|---|---|
| Principal Product | English muffins and soft rolls |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
180,000
ft2
|
| Annual Production | 99,473,267
lb
|
| Production Hrs. Annual | 7,800
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $853,395 | 15,296,852 |
kWh
|
$0.056 | |
| Electricity Demand | $133,763 | 33,574 |
kW-mo/yr
|
$3.98 | |
| Electricity Fees | $4,065 | - |
|
- | |
| Natural Gas | $458,724 | 78,556 |
MMBtu
|
$5.84 | |
| Waste Disposal Costs | |||||
| Water Usage | $95,161 | 10,574 |
Tgal
|
$9.00 | |
| Water Disposal | $126,883 | 10,574 |
Tgal
|
$12.00 | |
| Other Liquid (non-haz) | $604 | 1 |
gal
|
$604.00 | |
| TOTAL YEARLY COSTS | $1,672,595 | ||||
| RECOMMENDED SAVINGS* | $83,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4156: Use flow control valves on equipment to optimize water use | $37,800 | $1,039 | - | - |
$16,200
-
Tgal
|
$21,600
-
Tgal
|
|
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $19,330 | $720 |
$19,330
346,412
kWh
|
- | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $12,682 | $5,792 |
$12,682
227,270
kWh
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $11,142 | $4,800 |
$10,039
179,916
kWh
|
$1,103
-
kW-mo/yr
|
- | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $2,565 | $1,504 |
$2,565
45,964
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $83,520 | $13,855 |
$44,616
799,562
kWh
|
$1,103
-
kW-mo/yr
|
$16,200
-
Tgal
|
$21,600
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs