| Assessment Year | 2025 |
|---|---|
| Principal Product | Electrical and Electronic Components for Automobiles |
| NAICS | 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 265 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,314,669 | 26,298,595 |
kWh
|
$0.050 | |
| Electricity Demand | $568,767 | 54,686 |
kW-mo/yr
|
$10.40 | |
| Electricity Fees | $116,573 | - |
|
- | |
| Natural Gas | $424,512 | 231,018 |
MMBtu
|
$1.84 | |
| Waste Disposal Costs | |||||
| Water Usage | $147,527 | 27,396 |
Tgal
|
$5.38 | |
| Water Disposal | $213,773 | 27,542 |
Tgal
|
$7.76 | |
| Other Liquid (non-haz) | $5,087 | 1 |
gal
|
$5,087.00 | |
| TOTAL YEARLY COSTS | $2,790,908 | ||||
| RECOMMENDED SAVINGS* | $95,669 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8123: Pay utility bills on time | $11,153 | - | - | - | $6,309 |
$982
-
MMBtu
|
$3,862
-
gal
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,992 | $953 |
$16,337
326,740
kWh
|
$4,655
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $4,431 | - |
$4,431
88,625
kWh
|
- | - | - | - | - | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $57,613 | $3,735 |
$28,352
567,046
kWh
|
- | - |
$29,261
-
MMBtu
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,480 | $1,208 |
$377
7,540
kWh
|
$384
-
kW-mo/yr
|
- | - | - | $719 | |
| TOTAL RECOMMENDED | $95,669 | $5,896 |
$49,497
989,951
kWh
|
$5,039
-
kW-mo/yr
|
$6,309 |
$30,243
-
MMBtu
|
$3,862
-
gal
|
$719 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs