| Assessment Year | 2025 |
|---|---|
| Principal Product | education |
| NAICS | 611110: Elementary and Secondary Schools |
| SIC | 8211: Elementary and Secondary Schools |
| Sales Range | less than $500 k |
| # of Employees | 100 |
| Plant Area |
97,800
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 1,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $55,140 | 891,828 |
kWh
|
$0.062 | |
| Natural Gas | $15,332 | 3,061 |
MMBtu
|
$5.01 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,140 | 476 |
Tgal
|
$15.00 | |
| TOTAL YEARLY COSTS | $77,612 | ||||
| RECOMMENDED SAVINGS* | $18,231 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2628: Utilize a less expensive cooling method | $1,599 | $2,000 |
$603
9,745
kWh
|
$996
-
MMBtu
|
|
| 02 | 2.2628: Utilize a less expensive cooling method | $861 | $2,000 |
$861
13,922
kWh
|
- | |
| 03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $767 | $10,000 | - |
$767
-
MMBtu
|
|
| 04 | 2.2628: Utilize a less expensive cooling method | $120 | $300 |
$120
1,944
kWh
|
- | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $630 | $30,000 |
$(-1,348.0)
(-21,801)
kWh
|
$1,978
-
MMBtu
|
|
| 06 | 2.6125: Keep equipment clean | $969 | $500 |
$969
15,678
kWh
|
- | |
| 07 | 2.9114: Use solar heat to make electricty | $13,285 | $224,000 |
$13,285
214,872
kWh
|
- | |
| TOTAL RECOMMENDED | $18,231 | $268,800 |
$14,490
234,360
kWh
|
$3,741
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs