ITAC Assessment: UD1120
ITAC logo
ITAC Assessment: UD1120
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product education
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range less than $500
k
# of Employees 100
Plant Area 97,800
ft2
Annual Production 1
units
Production Hrs. Annual 1,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,140 891,828
kWh
Natural Gas $15,332 3,061
MMBtu
Waste Disposal Costs
Water Usage $7,140 476
Tgal
TOTAL YEARLY COSTS $77,612
RECOMMENDED SAVINGS* $18,231 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2628: Utilize a less expensive cooling method $1,599 $2,000 $603
9,745
kWh
$996
-
MMBtu
02 2.2628: Utilize a less expensive cooling method $861 $2,000 $861
13,922
kWh
-
03 2.2444: Use hot process fluids to preheat incoming process fluids $767 $10,000 - $767
-
MMBtu
04 2.2628: Utilize a less expensive cooling method $120 $300 $120
1,944
kWh
-
05 2.4322: Use or replace with energy efficient substitutes $630 $30,000 $(-1,348.0)
(-21,801)
kWh
$1,978
-
MMBtu
06 2.9114: Use solar heat to make electricty $969 $500 $969
15,678
kWh
-
07 2.9114: Use solar heat to make electricty $13,285 $224,000 $13,285
214,872
kWh
-
TOTAL RECOMMENDED $18,231 $268,800 $14,490
234,360
kWh
$3,741
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs