ITAC Assessment: UD1119
ITAC logo
ITAC Assessment: UD1119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product law enforcement
NAICS 922140: Correctional Institutions
SIC 8744: Facilities Support Management Services
Sales Range less than $500
k
# of Employees 20
Plant Area 12,750
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,383 692,550
kWh
Natural Gas $4,504 517
MMBtu
Waste Disposal Costs
Water Usage $1,812 594
Tgal
TOTAL YEARLY COSTS $77,699
RECOMMENDED SAVINGS* $47,679 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,511 $40,000 $8,511
82,632
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,147 $16,000 $6,147
59,679
kWh
-
03 2.9114: Use solar heat to make electricty $7,022 $100,000 $7,022
68,174
kWh
-
04 2.2628: Utilize a less expensive cooling method $855 $550 $855
8,300
kWh
-
05 2.4322: Use or replace with energy efficient substitutes $649 $6,400 - $649
-
MMBtu
06 2.7234: Use heat pump for space conditioning $24,495 $100,000 $23,520
228,350
kWh
$975
-
MMBtu
TOTAL RECOMMENDED $47,679 $262,950 $46,055
447,135
kWh
$1,624
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs