| Assessment Year | 2025 |
|---|---|
| Principal Product | Packaging Products, including Gallon jugs, aerosol containers, and plastic bottles, etc. |
| NAICS | 326160: Plastics Bottle Manufacturing |
| SIC | 3085: Plastics Bottles |
| Sales Range | $100 M to 500M |
| # of Employees | 227 |
| Plant Area |
268,000
ft2
|
| Annual Production | 1,835,686,776
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $2,069,472 | 56,965,788 |
kWh
|
$0.036 | |
| Electricity Demand | $628,074 | 106,390 |
kW-mo/yr
|
$5.90 | |
| Electricity Fees | $3,840 | - |
|
- | |
| Natural Gas | $43,586 | 12,125 |
MMBtu
|
$3.59 | |
| Waste Disposal Costs | |||||
| Water Usage | $62,698 | 14,365 |
Tgal
|
$4.36 | |
| Water Disposal | $12,839 | 1 |
Tgal
|
$12,839.00 | |
| TOTAL YEARLY COSTS | $2,820,509 | ||||
| RECOMMENDED SAVINGS* | $92,877 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $23,965 | $2,310 |
$19,601
539,971
kWh
|
$4,364
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $24,579 | - |
$20,071
552,931
kWh
|
$4,508
-
kW-mo/yr
|
- | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $2,017 | $2,784 |
$1,962
54,055
kWh
|
$55
-
kW-mo/yr
|
- | - | |
| 04 | 2.2628: Utilize a less expensive cooling method | $41,149 | $75,000 |
$33,653
927,097
kWh
|
$7,496
-
kW-mo/yr
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $1,167 | $4,639 |
$211
5,804
kWh
|
$142
-
kW-mo/yr
|
$580 | $234 | |
| TOTAL RECOMMENDED | $92,877 | $84,733 |
$75,498
2,079,858
kWh
|
$16,565
-
kW-mo/yr
|
$580 | $234 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs