| Assessment Year | 2025 |
|---|---|
| Principal Product | Aircraft Components |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
112,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $5,564,175 | 70,790,181 |
kWh
|
$0.079 | |
| Electricity Demand | $599,324 | 96,727 |
kW-mo/yr
|
$6.20 | |
| Electricity Fees | $9,452 | - |
|
- | |
| Natural Gas | $1,288,461 | 360,054 |
MMBtu
|
$3.58 | |
| Other Energy | $9,007 | 1 |
MMBtu
|
$9,007.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $559,131 | 341,829 |
Tgal
|
$1.64 | |
| Water Disposal | $559,135 | 341,829 |
Tgal
|
$1.64 | |
| TOTAL YEARLY COSTS | $8,588,685 | ||||
| RECOMMENDED SAVINGS* | $478,265 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $21,247 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7233: Use properly designed and sized hvac equipment | $52,334 | - |
$47,687
547,500
kWh
|
$4,647
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $1,107 | $2,722 |
$1,107
12,740
kWh
|
- | - | - | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $798 | $1,000 |
$(-136.0)
(-1,564)
kWh
|
$(-29.0)
-
kW-mo/yr
|
$963
-
MMBtu
|
- | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $61,605 | $8,161 |
$56,008
644,515
kWh
|
$5,597
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $15,572 | $16,800 |
$15,572
178,779
kWh
|
- | - | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,527 | $900 |
$5,036
57,816
kWh
|
$491
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.4322: Use or replace with energy efficient substitutes | $326,496 | $385,000 | - | - |
$326,496
-
MMBtu
|
- | - | - | |
| 08 | 2.3212: Optimize plant power factor | $9,007 | $30,514 | - | - | - |
$9,007
-
MMBtu
|
- | - | |
| 09 | 2.7233: Use properly designed and sized hvac equipment | $5,671 | - |
$3,998
45,900
kWh
|
$1,673
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 2.7135: Install occupancy sensors | $148 | $449 |
$104
1,200
kWh
|
$31
-
kW-mo/yr
|
- | - | $8 | $5 | |
| TOTAL RECOMMENDED | $478,265 | $445,546 |
$129,376
1,486,886
kWh
|
$12,410
-
kW-mo/yr
|
$327,459
-
MMBtu
|
$9,007
-
MMBtu
|
$8 | $5 | ||
| TOTAL IMPLEMENTED | $21,247 | $18,149 |
$20,712
237,795
kWh
|
$522
-
kW-mo/yr
|
- | - | $8 | $5 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs