Assessment Year | 2024 |
---|---|
Principal Product | Injection Molded and Extruded Plastic Components for Motor Vehicles |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
280,000
ft2
|
Annual Production | 13,759,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,107,886 | 14,627,293 |
kWh
|
$0.076 | |
Electricity Demand | $207,581 | 30,254 |
kW-mo/yr
|
$6.86 | |
Electricity Fees | $17,275 | - |
|
- | |
Natural Gas | $46,756 | 8,934 |
MMBtu
|
$5.23 | |
Waste Disposal Costs | |||||
Water Usage | $25,674 | 45 |
Tgal
|
$570.53 | |
Water Disposal | $17,561 | 44 |
Tgal
|
$399.11 | |
TOTAL YEARLY COSTS | $1,422,733 | ||||
RECOMMENDED SAVINGS* | $97,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $13,379 | $1,330 |
$12,093
159,747
kWh
|
$367
-
kW-mo/yr
|
- |
$919
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,271 | $772 |
$5,765
76,159
kWh
|
$103
-
kW-mo/yr
|
- |
$403
-
MMBtu
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $7,247 | $720 |
$6,135
81,042
kWh
|
$1,112
-
kW-mo/yr
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $5,446 | $9,639 |
$4,610
60,900
kWh
|
$836
-
kW-mo/yr
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $2,522 | $2,450 |
$2,522
33,311
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,442 | $953 |
$1,221
16,129
kWh
|
$221
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $32,360 | $48,200 |
$28,786
380,270
kWh
|
$3,574
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,573 | $48,200 |
$13,853
183,009
kWh
|
$1,720
-
kW-mo/yr
|
- | - | |
09 | 2.3212: Optimize plant power factor | $13,480 | $31,200 | - | - | $13,480 | - | |
TOTAL RECOMMENDED | $97,720 | $143,464 |
$74,985
990,567
kWh
|
$7,933
-
kW-mo/yr
|
$13,480 |
$1,322
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs