ITAC Assessment: UD1080
ITAC logo
ITAC Assessment: UD1080
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal displays
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 63
Plant Area 105,000
ft2
Annual Production 411,890
units
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,212 885,880
kWh
Electricity Demand $58,182 3,671
kW-mo/yr
Electricity Fees $226 -
Natural Gas $21,905 4,889
MMBtu
Waste Disposal Costs
Water Usage $3,164 1,474
Tgal
Water Disposal $3,333 1,474
Tgal
Other Liquid (non-haz) $487 1
gal
TOTAL YEARLY COSTS $128,509
RECOMMENDED SAVINGS* $15,118 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,367

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $808 $941 $808
17,184
kWh
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $165 - $56
1,198
kWh
$109
-
kW-mo/yr
- - -
03 2.1114: Limit and control secondary combustion air in furnace $1,555 $405 $180
3,879
kWh
- $1,375
-
MMBtu
- -
04 2.4239: Eliminate or reduce compressed air usage $31 $142 $31
652
kWh
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,018 $924 $1,219
25,201
kWh
$799
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $10,541 $11,151 $3,971
85,388
kWh
$2,603
-
kW-mo/yr
- $1,562 $2,405
TOTAL RECOMMENDED $15,118 $13,562 $6,265
133,502
kWh
$3,511
-
kW-mo/yr
$1,375
-
MMBtu
$1,562 $2,405
TOTAL IMPLEMENTED $13,367 $13,015 $5,998
127,773
kWh
$3,402
-
kW-mo/yr
- $1,562 $2,405
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs