| Assessment Year | 2024 |
|---|---|
| Principal Product | Food Manufacturing |
| NAICS | 311999: All Other Miscellaneous Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 500 |
| Plant Area |
182,000
ft2
|
| Annual Production | 118,362,121
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $870,185 | 12,502,886 |
kWh
|
$0.070 | |
| Electricity Demand | $214,152 | 32,425 |
kW-mo/yr
|
$6.60 | |
| Electricity Fees | $1,493 | - |
|
- | |
| Natural Gas | $521,925 | 119,099 |
MMBtu
|
$4.38 | |
| Other Gas | $2,574 | 1 |
MMBtu
|
$2,574.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $254,930 | 62,449 |
Tgal
|
$4.08 | |
| Water Disposal | $267,115 | 41,507 |
Tgal
|
$6.44 | |
| Other Liquid (non-haz) | $262,895 | 1 |
gal
|
$262,895.00 | |
| TOTAL YEARLY COSTS | $2,395,269 | ||||
| RECOMMENDED SAVINGS* | $210,619 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $189,908 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $338 | - | - |
$338
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $25,599 | $5,000 |
$25,599
367,808
kWh
|
- | - | - | - | - | |
| 03 | 2.2113: Repair or replace steam traps | $40,904 | - | - | - |
$40,904
-
MMBtu
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $20,373 | $76,500 |
$(-5,456.0)
(-78,388)
kWh
|
$(-709.0)
-
kW-mo/yr
|
$26,538
-
MMBtu
|
- | - | - | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,667 | $1,500 | - | - |
$9,667
-
MMBtu
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $38,311 | $1,011 |
$32,399
465,504
kWh
|
$5,912
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.4237: Substitute compressed air cooling with water or air cooling | $30,626 | $6,500 |
$27,103
389,411
kWh
|
$3,523
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $42,618 | $164,640 |
$28,351
407,347
kWh
|
$5,173
-
kW-mo/yr
|
- | - | - | $9,094 | |
| 09 | 2.7135: Install occupancy sensors | $2,183 | $2,500 |
$1,084
15,575
kWh
|
$197
-
kW-mo/yr
|
- | $431 | $471 | - | |
| TOTAL RECOMMENDED | $210,619 | $257,651 |
$109,080
1,567,257
kWh
|
$14,434
-
kW-mo/yr
|
$77,109
-
MMBtu
|
$431 | $471 | $9,094 | ||
| TOTAL IMPLEMENTED | $189,908 | $181,151 |
$114,536
1,645,645
kWh
|
$14,805
-
kW-mo/yr
|
$50,571
-
MMBtu
|
$431 | $471 | $9,094 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs