Assessment Year | 2003 |
---|---|
Principal Product | Rigid, Rigid Flex, and Flex PCBs |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 152 |
Plant Area |
35,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 6,072
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $260,590 | 2,141,487 |
kWh
|
$0.12 |
Electricity Demand | $60,386 | 7,368 |
kW-mo/yr
|
$8.20 |
Electricity Fees | $23,260 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,868 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,280 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $670 | $68 |
$585
4,023
kWh
|
$85
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,653 | $1,794 |
$1,576
11,840
kWh
|
$77
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $462 | $20 |
$420
3,158
kWh
|
$42
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,818 | - |
$2,562
19,250
kWh
|
$256
-
kW-mo/yr
|
- | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,443 | $102 |
$1,312
9,859
kWh
|
$131
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $92 | $87 |
$84
626
kWh
|
$8
-
kW-mo/yr
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,730 | $11,000 | - | - |
$8,730
-
Tgal
|
|
TOTAL RECOMMENDED | $15,868 | $13,071 |
$6,539
48,756
kWh
|
$599
-
kW-mo/yr
|
$8,730
-
Tgal
|
||
TOTAL IMPLEMENTED | $3,280 | $20 |
$2,982
22,408
kWh
|
$298
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs