ITAC Assessment: UD1076
ITAC logo
ITAC Assessment: UD1076
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Religious services and worship
NAICS 813110: Religious Organizations
SIC 8661: Religious Organizations
Sales Range less than $500
k
# of Employees 10
Plant Area 41,050
ft2
Annual Production 52
units
Production Hrs. Annual 2,158
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,288 245,331
kWh
Natural Gas $20,298 16
MMBtu
TOTAL YEARLY COSTS $61,586
RECOMMENDED SAVINGS* $37,073 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $4,155 - $2,910
24,250
kWh
$1,245
-
MMBtu
02 2.7424: Shade windows from summer sun $1,380 $8,000 $600
5,050
kWh
$780
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,098 $6,750 $2,098
17,480
kWh
-
04 2.9114: Use solar heat to make electricty $29,440 $362,600 $29,440
245,000
kWh
-
TOTAL RECOMMENDED $37,073 $377,350 $35,048
291,780
kWh
$2,025
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs