ITAC Assessment: UD1074
ITAC logo
ITAC Assessment: UD1074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 350,347
ft2
Annual Production 1,864,491
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $187,831 3,636,144
kWh
Electricity Demand $55,779 8,428
kW-mo/yr
Electricity Fees $552 -
Natural Gas $15,201 1,370
MMBtu
Other Gas $2,574 1
MMBtu
Waste Disposal Costs
Water Usage $25,859 5,040
Tgal
Water Disposal $25,142 5,040
Tgal
Other Liquid (non-haz) $300 1
gal
TOTAL YEARLY COSTS $313,238
RECOMMENDED SAVINGS* $81,971 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,516

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #1 Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings
01 2.3192: Use fossil fuel powered generator during peak demand periods $9,834 - $1,089
21,060
kWh
$15,035
-
kW-mo/yr
$(-6,290.0)
-
MMBtu
- - - -
02 2.2628: Utilize a less expensive cooling method $12,621 $12,700 $(-5,101.0)
(-98,673)
kWh
$(-895.0)
-
kW-mo/yr
- $9,437
-
Tgal
$9,180
-
Tgal
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,018 $8,430 $1,440
27,857
kWh
$253
-
kW-mo/yr
- - - $118 $207
04 2.4322: Use or replace with energy efficient substitutes $24,521 $7,100,000 $20,863
403,534
kWh
$3,658
-
kW-mo/yr
- - - - -
05 2.9114: Use solar heat to make electricty $32,977 $336,971 $39,881
771,717
kWh
- - - - $(-6,904.0) -
TOTAL RECOMMENDED $81,971 $7,458,101 $58,172
1,125,495
kWh
$18,051
-
kW-mo/yr
$(-6,290.0)
-
MMBtu
$9,437
-
Tgal
$9,180
-
Tgal
$(-6,786.0) $207
TOTAL IMPLEMENTED $59,516 $7,445,401 $62,184
1,203,108
kWh
$3,911
-
kW-mo/yr
- - - $(-6,786.0) $207
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs