Assessment Year | 2023 |
---|---|
Principal Product | Aircraft Parts |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
110,000
ft2
|
Annual Production | 3,782
units
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $224,826 | 3,827,497 |
kWh
|
$0.059 |
Electricity Demand | $42,294 | 8,470 |
kW-mo/yr
|
$4.99 |
Electricity Fees | $7,471 | - |
|
- |
Natural Gas | $37,092 | 3,838 |
MMBtu
|
$9.66 |
TOTAL YEARLY COSTS | $311,683 | |||
RECOMMENDED SAVINGS* | $53,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,253 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $5,952 | $600 |
$5,952
101,400
kWh
|
- | - | - | |
02 | 2.7241: Install outside air damper / economizer on hvac unit | $3,630 | $1,415 |
$3,630
61,838
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,718 | $952 |
$3,330
56,721
kWh
|
$388
-
kW-mo/yr
|
- | - | |
04 | 2.4239: Eliminate or reduce compressed air usage | $671 | $1,639 |
$671
11,438
kWh
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $1,566 | $1,770 |
$1,078
18,360
kWh
|
- | $155 | $333 | |
06 | 2.4313: Provide proper maintenance of motor driven equipment | $21,383 | $42,766 |
$21,383
365,270
kWh
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,743 | $18,195 |
$16,128
274,756
kWh
|
$615
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5 | - |
$5
87
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $53,668 | $67,337 |
$52,177
889,870
kWh
|
$1,003
-
kW-mo/yr
|
$155 | $333 | ||
TOTAL IMPLEMENTED | $10,253 | $3,654 |
$10,253
174,676
kWh
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs