| Assessment Year | 2023 |
|---|---|
| Principal Product | Steel Pipe and Tubes |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
425,000
ft2
|
| Annual Production | 54,013,022
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $383,160 | 7,255,710 |
kWh
|
$0.053 | |
| Electricity Demand | $475,730 | 31,401 |
kW-mo/yr
|
$15.15 | |
| Electricity Fees | $780 | - |
|
- | |
| Natural Gas | $115,057 | 19,525 |
MMBtu
|
$5.89 | |
| Waste Disposal Costs | |||||
| Water Usage | $20,944 | 2,043 |
Tgal
|
$10.25 | |
| Water Disposal | $18,274 | 2,043 |
Tgal
|
$8.94 | |
| TOTAL YEARLY COSTS | $1,013,945 | ||||
| RECOMMENDED SAVINGS* | $83,235 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $9,026 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $589 | - |
$272
5,159
kWh
|
$317
-
kW-mo/yr
|
- | - | - | |
| 02 | 3.4116: Meter recycled water (to reduce sewer charges) | $12,692 | $430 | - | - |
$12,692
-
Tgal
|
- | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $38,039 | - |
$24,513
464,256
kWh
|
$13,526
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $19,345 | $19,667 |
$7,117
134,784
kWh
|
$11,781
-
kW-mo/yr
|
- | $6 | $441 | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,046 | $952 |
$800
15,144
kWh
|
$1,246
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $210 | $741 |
$210
3,974
kWh
|
- | - | - | - | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $6,980 | $2,457 |
$6,980
132,198
kWh
|
- | - | - | - | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,334 | $3,051 |
$3,334
63,141
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $83,235 | $27,298 |
$43,226
818,656
kWh
|
$26,870
-
kW-mo/yr
|
$12,692
-
Tgal
|
$6 | $441 | ||
| TOTAL IMPLEMENTED | $9,026 | $3,409 |
$7,780
147,342
kWh
|
$1,246
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs