ITAC Assessment: UD1053
ITAC logo
ITAC Assessment: UD1053
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Medical Supplies
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $100
M
to 500
M
# of Employees 1,200
Plant Area 654,218
ft2
Annual Production 35,300,000
units
Production Hrs. Annual 4,800
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,155,109 42,500,772
kWh
Electricity Demand $473,583 93,610
kW-mo/yr
Electricity Fees $8,000 -
Natural Gas $68,833 9,588
MMBtu
Waste Disposal Costs
Water Usage $119,260 23,837
Tgal
Water Disposal $158,211 23,837
Tgal
TOTAL YEARLY COSTS $2,982,996
RECOMMENDED SAVINGS* $579,194 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $298,257

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $21,937 - $17,577
344,652
kWh
$4,360
-
kW-mo/yr
- - -
02 2.4239: Eliminate or reduce compressed air usage $6,508 $19,116 $6,508
127,600
kWh
- - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $103,216 $145,725 $92,608
1,815,839
kWh
$10,608
-
kW-mo/yr
- - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,943 - $6,996
136,589
kWh
$947
-
kW-mo/yr
- - -
05 2.7241: Install outside air damper / economizer on hvac unit $288,790 $110,000 $288,790
5,662,546
kWh
- - - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $95,100 $201,500 $83,721
1,641,582
kWh
$11,379
-
kW-mo/yr
- - -
07 2.7224: Reduce space conditioning during non-working hours $2,097 $110,000 $832
16,316
kWh
- - $1,265
-
MMBtu
-
08 2.7135: Install occupancy sensors $7,370 $110,000 $5,063
99,278
kWh
- - - $2,307
09 2.3212: Optimize plant power factor $46,233 $119,156 - - $46,233 - -
TOTAL RECOMMENDED $579,194 $815,497 $502,095
9,844,402
kWh
$27,294
-
kW-mo/yr
$46,233 $1,265
-
MMBtu
$2,307
TOTAL IMPLEMENTED $298,257 $330,000 $294,685
5,778,140
kWh
- - $1,265
-
MMBtu
$2,307
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs