Assessment Year | 2023 |
---|---|
Principal Product | Medical Supplies |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 1,200 |
Plant Area |
654,218
ft2
|
Annual Production | 35,300,000
units
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,155,109 | 42,500,772 |
kWh
|
$0.051 | |
Electricity Demand | $473,583 | 93,610 |
kW-mo/yr
|
$5.06 | |
Electricity Fees | $8,000 | - |
|
- | |
Natural Gas | $68,833 | 9,588 |
MMBtu
|
$7.18 | |
Waste Disposal Costs | |||||
Water Usage | $119,260 | 23,837 |
Tgal
|
$5.00 | |
Water Disposal | $158,211 | 23,837 |
Tgal
|
$6.64 | |
TOTAL YEARLY COSTS | $2,982,996 | ||||
RECOMMENDED SAVINGS* | $579,194 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $298,257 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $21,937 | - |
$17,577
344,652
kWh
|
$4,360
-
kW-mo/yr
|
- | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $6,508 | $19,116 |
$6,508
127,600
kWh
|
- | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $103,216 | $145,725 |
$92,608
1,815,839
kWh
|
$10,608
-
kW-mo/yr
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,943 | - |
$6,996
136,589
kWh
|
$947
-
kW-mo/yr
|
- | - | - | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $288,790 | $110,000 |
$288,790
5,662,546
kWh
|
- | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $95,100 | $201,500 |
$83,721
1,641,582
kWh
|
$11,379
-
kW-mo/yr
|
- | - | - | |
07 | 2.7224: Reduce space conditioning during non-working hours | $2,097 | $110,000 |
$832
16,316
kWh
|
- | - |
$1,265
-
MMBtu
|
- | |
08 | 2.7135: Install occupancy sensors | $7,370 | $110,000 |
$5,063
99,278
kWh
|
- | - | - | $2,307 | |
09 | 2.3212: Optimize plant power factor | $46,233 | $119,156 | - | - | $46,233 | - | - | |
TOTAL RECOMMENDED | $579,194 | $815,497 |
$502,095
9,844,402
kWh
|
$27,294
-
kW-mo/yr
|
$46,233 |
$1,265
-
MMBtu
|
$2,307 | ||
TOTAL IMPLEMENTED | $298,257 | $330,000 |
$294,685
5,778,140
kWh
|
- | - |
$1,265
-
MMBtu
|
$2,307 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs