Assessment Year | 1985 |
---|---|
Principal Product | ICE CREAM,KEFIR,EGGNOG |
NAICS |
n/a
|
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $1 M to 5M |
# of Employees | 7 |
Plant Area |
n/a
|
Annual Production | 140
Tgal
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,032 | 341,735 |
kWh
|
$0.076 |
Fuel Oil #2 | $4,443 | 601 |
MMBtu
|
$7.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,851 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,628 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.2447: Heat water with exhaust heat | $2,163 | $1,875 |
$2,163
28,429
kWh
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $753 | $1,827 |
$1,293
16,999
kWh
|
$(-540.0)
-
MMBtu
|
|
03 | 2.1221: Replace obsolete burners with more efficient ones | $160 | $154 | - |
$160
-
MMBtu
|
|
04 | 2.2444: Use hot process fluids to preheat incoming process fluids | $283 | - | - |
$283
-
MMBtu
|
|
05 | 2.3212: Optimize plant power factor | $432 | $289 |
$432
-
kWh
|
- | |
06 | 2.3191: Use demand controller or load shedder | $1,060 | $1,190 |
$1,060
-
kWh
|
- | |
TOTAL RECOMMENDED | $4,851 | $5,335 |
$4,948
45,428
kWh
|
$(-97.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,628 | $2,270 |
$1,725
16,999
kWh
|
$(-97.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs