| Assessment Year | 2023 |
|---|---|
| Principal Product | Automotive Shock Absorbers |
| NAICS | 336340: Motor Vehicle Brake System Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 420 |
| Plant Area |
135,300
ft2
|
| Annual Production | 7,595,120
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $960,587 | 17,299,200 |
kWh
|
$0.056 | |
| Electricity Demand | $995,183 | 46,613 |
kW-mo/yr
|
$21.35 | |
| Electricity Fees | $1,944 | - |
|
- | |
| Natural Gas | $213,604 | 38,453 |
MMBtu
|
$5.55 | |
| Waste Disposal Costs | |||||
| Water Usage | $62,700 | 9,788 |
Tgal
|
$6.41 | |
| Water Disposal | $93,859 | 9,788 |
Tgal
|
$9.59 | |
| TOTAL YEARLY COSTS | $2,327,877 | ||||
| RECOMMENDED SAVINGS* | $113,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $46,988 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,427 | - |
$3,079
54,980
kWh
|
$2,348
-
kW-mo/yr
|
- | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,718 | $6,322 |
$12,296
219,575
kWh
|
$6,422
-
kW-mo/yr
|
- | - | |
| 03 | 2.7241: Install outside air damper / economizer on hvac unit | $14,073 | - |
$14,073
251,310
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,488 | $952 |
$18,057
322,449
kWh
|
$9,431
-
kW-mo/yr
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $13,453 | $9,000 |
$(-110.0)
(-1,964)
kWh
|
$(-119.0)
-
kW-mo/yr
|
$13,682
-
MMBtu
|
- | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $34,801 | $16,950 | - | - | - |
$34,801
-
Tgal
|
|
| TOTAL RECOMMENDED | $113,960 | $33,224 |
$47,395
846,350
kWh
|
$18,082
-
kW-mo/yr
|
$13,682
-
MMBtu
|
$34,801
-
Tgal
|
||
| TOTAL IMPLEMENTED | $46,988 | $952 |
$35,209
628,739
kWh
|
$11,779
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs