ITAC Assessment: BD0375
ITAC logo
ITAC Assessment: BD0375
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product ASME Pressure Vessels
NAICS 332420: Metal Tank (Heavy Gauge) Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 38
Plant Area 40,000
ft2
Annual Production 100
pieces
Production Hrs. Annual 3,744
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,346 612,400
kWh
Electricity Demand $7,187 1,240
kW-mo/yr
Electricity Fees $10,251 -
Natural Gas $24,359 2,437
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,091 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,405

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7231: Use radiant heater for spot heating $7,334 $3,180 - - $7,334
-
MMBtu
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,652 $16,478 $3,247
47,133
kWh
$874
-
kW-mo/yr
- - $106 - $425
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,271 $900 $2,576
37,385
kWh
$695
-
kW-mo/yr
- - - - -
04 2.7145: Install skylights $1,922 $2,547 $1,922
27,900
kWh
- - - - - -
05 2.7135: Install occupancy sensors $1,134 $750 $1,090
12,600
kWh
$44
-
kW-mo/yr
- - - - -
06 2.7111: Reduce illumination to minimum necessary levels $907 $104 $715
10,389
kWh
$192
-
kW-mo/yr
- - - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $556 $15 $438
6,368
kWh
$118
-
kW-mo/yr
- - - - -
08 2.4133: Use most efficient type of electric motors $277 $700 $204
2,964
kWh
$73
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $204 $250 $183
2,663
kWh
$21
-
kW-mo/yr
- - - - -
10 3.2123: Convert to high volume low pressure (hvlp) paint guns $12,834 $3,400 - - - $1,369
-
gal
- $11,465 -
TOTAL RECOMMENDED $33,091 $28,324 $10,375
147,402
kWh
$2,017
-
kW-mo/yr
$7,334
-
MMBtu
$1,369
-
gal
$106 $11,465 $425
TOTAL IMPLEMENTED $4,405 $1,650 $3,666
49,985
kWh
$739
-
kW-mo/yr
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs