Assessment Year | 2021 |
---|---|
Principal Product | HVAC Assembly and Injection Molding |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 302 |
Plant Area |
131,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $328,046 | 8,103,900 |
kWh
|
$0.040 | |
Electricity Demand | $459,835 | 18,247 |
kW-mo/yr
|
$25.20 | |
Electricity Fees | $11,177 | - |
|
- | |
Natural Gas | $16,951 | 3,101 |
MMBtu
|
$5.47 | |
Waste Disposal Costs | |||||
Water Usage | $7,949 | 2,323 |
Tgal
|
$3.42 | |
Water Disposal | $1,738 | 212 |
Tgal
|
$8.20 | |
TOTAL YEARLY COSTS | $825,696 | ||||
RECOMMENDED SAVINGS* | $65,943 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $45,045 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,340 | - |
$3,340
82,502
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $281 | - |
$125
3,096
kWh
|
$156
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $11,468 | $4,319 |
$5,108
126,183
kWh
|
$6,360
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,026 | $340 |
$1,793
44,301
kWh
|
$2,233
-
kW-mo/yr
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,569 | $35 |
$699
17,269
kWh
|
$870
-
kW-mo/yr
|
- | |
06 | 2.4131: Size electric motors for peak operating efficiency | $5,833 | $4,000 |
$3,148
77,766
kWh
|
$2,685
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,553 | $21,607 |
$7,783
192,297
kWh
|
$8,561
-
kW-mo/yr
|
$1,209 | |
08 | 2.2511: Insulate bare equipment | $20,126 | $28,000 |
$10,355
256,303
kWh
|
$9,771
-
kW-mo/yr
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,747 | $7,500 |
$1,747
43,167
kWh
|
- | - | |
TOTAL RECOMMENDED | $65,943 | $65,801 |
$34,098
842,884
kWh
|
$30,636
-
kW-mo/yr
|
$1,209 | ||
TOTAL IMPLEMENTED | $45,045 | $49,947 |
$23,271
575,403
kWh
|
$20,565
-
kW-mo/yr
|
$1,209 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs