| Assessment Year | 2020 |
|---|---|
| Principal Product | Ice Cream and Beverages |
| NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
| SIC | 2024: Ice Cream and Frozen Desserts |
| Sales Range | $100 M to 500M |
| # of Employees | 185 |
| Plant Area |
145,350
ft2
|
| Annual Production | 31,000
Tgal
|
| Production Hrs. Annual | 8,112
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $2,012,116 | 44,713,681 |
kWh
|
$0.045 | |
| Electricity Demand | $397,832 | 99,210 |
kW-mo/yr
|
$4.01 | |
| Natural Gas | $175,109 | 54,397 |
MMBtu
|
$3.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $312,439 | 87,924 |
Tgal
|
$3.55 | |
| Water Disposal | $1,737,246 | 38,169 |
Tgal
|
$45.52 | |
| TOTAL YEARLY COSTS | $4,634,742 | ||||
| RECOMMENDED SAVINGS* | $1,247,486 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $515 | - |
$455
10,112
kWh
|
$60
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $62,174 | $26,600 |
$16,123
358,284
kWh
|
- |
$46,051
-
MMBtu
|
- | - | - | |
| 03 | 2.2696: Use excess cold process fluid for industrial cooling needs | $25,124 | - |
$22,391
497,568
kWh
|
$2,733
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.5194: Redesign process | $43,180 | $20,000 | - | - |
$1,335
-
MMBtu
|
$3,072
-
Tgal
|
$38,773
-
Tgal
|
- | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $1,584 | $1,500 |
$1,401
31,140
kWh
|
$183
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.1221: Replace obsolete burners with more efficient ones | $16,717 | $64,900 | - | - |
$16,717
-
MMBtu
|
- | - | - | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,072 | - | - | - |
$1,072
-
MMBtu
|
- | - | - | |
| 08 | 2.2511: Insulate bare equipment | $359 | $392 | - | - |
$359
-
MMBtu
|
- | - | - | |
| 09 | 3.4131: Minimize contamination of water before treatment | $1,096,761 | $5,000,000 | - | - | - | - | - | $1,096,761 | |
| TOTAL RECOMMENDED | $1,247,486 | $5,113,392 |
$40,370
897,104
kWh
|
$2,976
-
kW-mo/yr
|
$65,534
-
MMBtu
|
$3,072
-
Tgal
|
$38,773
-
Tgal
|
$1,096,761 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs