ITAC Assessment: SF0087
ITAC logo
ITAC Assessment: SF0087
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Metal Products
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 120,000
ft2
Annual Production 16,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $414,417 6,248,535
kWh
Electricity Demand $157,834 11,907
kW-mo/yr
Natural Gas $74,677 27,739
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $141,327 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,438

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,390 $33,600 $6,591
99,355
kWh
$4,799
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $3,081 $3,839 $2,149
32,532
kWh
$932
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $1,101 $960 $688
10,258
kWh
$413
-
kW-mo/yr
- - -
04 2.6218: Turn off equipment when not in use $2,210 $2,600 $1,596
24,033
kWh
$614
-
kW-mo/yr
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,251 $1,265 $1,192
17,878
kWh
$1,059
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,036 - $5,673
85,287
kWh
$1,363
-
kW-mo/yr
- - -
07 2.2122: Install / repair insulation on condensate lines $353 $613 - - $353
-
MMBtu
- -
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $4,377 $14,820 - - $4,377
-
MMBtu
- -
09 2.8114: Change rate schedules or other changes in utility service $79,567 $140,000 - - - - $79,567
10 2.3212: Optimize plant power factor $1,979 $2,231 - $1,979
-
kW-mo/yr
- - -
11 2.4239: Eliminate or reduce compressed air usage $9,059 $5,330 $6,861
103,458
kWh
$2,198
-
kW-mo/yr
- - -
12 2.4239: Eliminate or reduce compressed air usage $3,369 $4,210 $2,137
32,239
kWh
$1,232
-
kW-mo/yr
- - -
13 2.3132: Recharge batteries on during off-peak demand periods $8,603 $1,329 - $8,603
-
kW-mo/yr
- - -
14 2.4231: Reduce the pressure of compressed air to the minimum required $868 $1,375 $665
9,965
kWh
$203
-
kW-mo/yr
- - -
15 3.4111: Use closed cycle process to minimize waste water production $3,998 $3,435 - - - $3,998
-
Tgal
-
16 3.4155: Meter waste water $2,085 $4,500 - - - $2,085
-
Tgal
-
TOTAL RECOMMENDED $141,327 $220,107 $27,552
415,005
kWh
$23,395
-
kW-mo/yr
$4,730
-
MMBtu
$6,083
-
Tgal
$79,567
TOTAL IMPLEMENTED $38,438 $57,470 $21,214
319,753
kWh
$13,226
-
kW-mo/yr
- $3,998
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs