ITAC Assessment: MZ0187
ITAC logo
ITAC Assessment: MZ0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product extruded aluminum products
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3334: Primary Production of Aluminum
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 77,940
ft2
Annual Production 6,600,000
lb
Production Hrs. Annual 8,064
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,207 3,240,000
kWh
Electricity Demand $44,789 12,721
kW-mo/yr
Natural Gas $154,660 23,624
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,585 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,736

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1121: Use insulation in furnaces to facilitate heating / cooling $849 $225 - $849
-
MMBtu
02 2.2424: Use heat in flue gases to preheat products or materials $9,635 $6,500 - $9,635
-
MMBtu
03 2.1135: Repair furnaces and oven doors so that they seal efficiently $684 $380 - $684
-
MMBtu
04 2.4239: Eliminate or reduce compressed air usage $1,096 $5,600 $1,096
15,660
kWh
-
05 2.2135: Repair and eliminate steam leaks $3,321 $1,440 - $3,321
-
MMBtu
TOTAL RECOMMENDED $15,585 $14,145 $1,096
15,660
kWh
$14,489
-
MMBtu
TOTAL IMPLEMENTED $14,736 $13,920 $1,096
15,660
kWh
$13,640
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs