| Assessment Year | 2020 |
|---|---|
| Principal Product | Diary (Milk, Cheese, Sour Cream) |
| NAICS | 311511: Fluid Milk Manufacturing |
| SIC | 2026: Fluid Milk |
| Sales Range | $50 M to 100M |
| # of Employees | 133 |
| Plant Area |
132,800
ft2
|
| Annual Production | 305,495,091
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $732,572 | 11,628,120 |
kWh
|
$0.063 | |
| Electricity Demand | $9,621 | 2,364 |
kW-mo/yr
|
$4.07 | |
| Electricity Fees | $118,007 | - |
|
- | |
| Natural Gas | $288,157 | 64,029 |
MMBtu
|
$4.50 | |
| Waste Disposal Costs | |||||
| Water Usage | $265,384 | 71,928 |
Tgal
|
$3.69 | |
| TOTAL YEARLY COSTS | $1,413,741 | ||||
| RECOMMENDED SAVINGS* | $124,889 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $12,065 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,207 | - |
$2,946
46,756
kWh
|
$261
-
kW-mo/yr
|
- | - | |
| 02 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $6,248 | $309 |
$5,740
91,104
kWh
|
$508
-
kW-mo/yr
|
- | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,267 | - | - | - |
$2,267
-
MMBtu
|
- | |
| 04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $769 | $1,080 | - | - |
$769
-
MMBtu
|
- | |
| 05 | 2.2627: Use multiple-effect evaporators | $18,945 | $26,742 |
$17,405
276,269
kWh
|
$1,540
-
kW-mo/yr
|
- | - | |
| 06 | 2.2628: Utilize a less expensive cooling method | $7,958 | - |
$6,761
107,310
kWh
|
$1,197
-
kW-mo/yr
|
- | - | |
| 07 | 2.2696: Use excess cold process fluid for industrial cooling needs | $6,591 | - |
$4,305
68,328
kWh
|
$2,286
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $60,442 | $86,373 |
$50,592
803,040
kWh
|
$3,847
-
kW-mo/yr
|
- | $6,003 | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,052 | $1,854 |
$8,095
128,498
kWh
|
$702
-
kW-mo/yr
|
- | $255 | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,410 | $28,400 |
$8,473
134,490
kWh
|
$937
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $124,889 | $144,758 |
$104,317
1,655,795
kWh
|
$11,278
-
kW-mo/yr
|
$3,036
-
MMBtu
|
$6,258 | ||
| TOTAL IMPLEMENTED | $12,065 | - |
$7,251
115,084
kWh
|
$2,547
-
kW-mo/yr
|
$2,267
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs