| Assessment Year | 2018 |
|---|---|
| Principal Product | Human Prosthetics |
| NAICS | 339999: All Other Miscellaneous Manufacturing |
| SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
82,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 7,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $221,894 | 2,334,327 |
kWh
|
$0.095 |
| Electricity Demand | $18,690 | 9,345 |
kW-mo/yr
|
$2.00 |
| Electricity Fees | $2,760 | - |
|
- |
| Natural Gas | $11,666 | 1,731 |
MMBtu
|
$6.74 |
| TOTAL YEARLY COSTS | $255,010 | |||
| RECOMMENDED SAVINGS* | $40,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,508 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $27,720 | - | - | - | $27,720 | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $392 | - |
$328
3,947
kWh
|
$64
-
kW-mo/yr
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $302 | - |
$286
3,463
kWh
|
$16
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $2,531 | $2,940 |
$2,032
24,600
kWh
|
$236
-
kW-mo/yr
|
$263 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,977 | $9,300 |
$4,662
56,453
kWh
|
$542
-
kW-mo/yr
|
$773 | |
| 06 | 2.2514: Cover open tanks | $3,170 | $5,040 |
$2,824
34,200
kWh
|
$346
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $40,092 | $17,280 |
$10,132
122,663
kWh
|
$1,204
-
kW-mo/yr
|
$28,756 | ||
| TOTAL IMPLEMENTED | $8,508 | $12,240 |
$6,694
81,053
kWh
|
$778
-
kW-mo/yr
|
$1,036 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs