Assessment Year | 2018 |
---|---|
Principal Product | Extruded Rubber Profile |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
Sales Range | $5 M to 10M |
# of Employees | 21 |
Plant Area |
42,000
ft2
|
Annual Production | 45,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $102,590 | 1,578,305 |
kWh
|
$0.065 | |
Electricity Demand | $13,355 | 2,446 |
kW-mo/yr
|
$5.46 | |
Natural Gas | $2,132 | 391 |
MMBtu
|
$5.45 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $22,500 | 30,000 |
lb
|
$0.75 | |
TOTAL YEARLY COSTS | $140,577 | ||||
RECOMMENDED SAVINGS* | $54,721 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $6,505 | - |
$5,850
90,000
kWh
|
$655
-
kW-mo/yr
|
- | - | - | |
02 | 2.2515: Use optimum thickness insulation | $2,434 | $2,072 |
$2,084
32,076
kWh
|
$350
-
kW-mo/yr
|
- | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $7,256 | $3,172 |
$6,212
95,570
kWh
|
$1,044
-
kW-mo/yr
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $291 | - |
$95
1,455
kWh
|
$196
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,805 | $2,571 |
$3,875
59,616
kWh
|
$723
-
kW-mo/yr
|
- | - | $207 | |
06 | 2.7135: Install occupancy sensors | $1,216 | $595 |
$943
14,515
kWh
|
$157
-
kW-mo/yr
|
- | - | $116 | |
07 | 3.5314: Use in-process recycling whenever possible | $22,500 | $20,000 | - | - | - |
$22,500
-
lb
|
- | |
08 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,857 | $11,500 |
$4,720
72,614
kWh
|
$1,137
-
kW-mo/yr
|
- | - | - | |
09 | 3.4114: Replace city water with recycled water via cooling tower | $3,857 | $6,000 |
$(-488.0)
(-7,503)
kWh
|
- |
$4,345
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $54,721 | $45,910 |
$23,291
358,343
kWh
|
$4,262
-
kW-mo/yr
|
$4,345
-
Tgal
|
$22,500
-
lb
|
$323 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs