ITAC Assessment: UD0964
ITAC logo
ITAC Assessment: UD0964
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Paper Food Packaging
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 152
Plant Area 130,000
ft2
Annual Production 23,985,229
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $309,201 4,045,111
kWh
Electricity Demand $42,964 10,356
kW-mo/yr
Natural Gas $31,218 6,703
MMBtu
Waste Disposal Costs
Water Usage $8,751 707
Tgal
Water Disposal $7,553 707
Tgal
TOTAL YEARLY COSTS $399,687
RECOMMENDED SAVINGS* $76,501 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $6,083 - $10,054
131,609
kWh
$2,590
-
kW-mo/yr
$(-6,561.0)
-
MMBtu
- -
02 2.2211: Use optimum temperature $652 $500 - - $652
-
MMBtu
- -
03 3.4116: Meter recycled water (to reduce sewer charges) $5,847 $500 - - - $5,847
-
Tgal
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,000 $1,000 $9,586
125,493
kWh
$1,134
-
kW-mo/yr
- - $(-720.0)
05 2.4239: Eliminate or reduce compressed air usage $4,749 $2,840 $4,246
55,589
kWh
$503
-
kW-mo/yr
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $3,522 - $3,149
41,223
kWh
$373
-
kW-mo/yr
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,348 $36,424 $28,027
367,321
kWh
$3,321
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $8,225 $21,449 $7,355
96,288
kWh
$870
-
kW-mo/yr
- - -
09 2.7144: Install spectral reflectors / delamp $6,075 - $5,048
66,079
kWh
$597
-
kW-mo/yr
- - $430
TOTAL RECOMMENDED $76,501 $62,713 $67,465
883,602
kWh
$9,388
-
kW-mo/yr
$(-5,909.0)
-
MMBtu
$5,847
-
Tgal
$(-290.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs