ITAC Assessment: UD0960
ITAC logo
ITAC Assessment: UD0960
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Metal Forming Machinery
NAICS 333517: Machine Tool Manufacturing
SIC 3542: Machine Tools, Metal Forming Types
Sales Range $50
M
to 100
M
# of Employees 425
Plant Area 600,000
ft2
Annual Production 50
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $796,048 9,756,000
kWh
Electricity Demand $184,509 22,140
kW-mo/yr
Electricity Fees $7,709 -
Natural Gas $123,045 27,135
MMBtu
TOTAL YEARLY COSTS $1,111,311
RECOMMENDED SAVINGS* $121,634 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,572

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings
01 2.7224: Reduce space conditioning during non-working hours $10,202 - $56
649
kWh
- $10,146
-
MMBtu
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,385 - $13,427
154,703
kWh
$1,958
-
kW-mo/yr
- - - - -
03 2.6218: Turn off equipment when not in use $10,808 - $10,808
124,530
kWh
- - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,390 $1,000 $3,838
44,226
kWh
$560
-
kW-mo/yr
- - - - $(-1,008.0)
05 2.6212: Turn off equipment during breaks, reduce operating time $17,273 - $9,671
111,427
kWh
$1,352
-
kW-mo/yr
- - $2,172
-
Tgal
$4,078
-
Tgal
-
06 2.2625: Chill water to the highest temperature possible $514 $1,425 $514
5,919
kWh
- - - - - -
07 2.2414: Use waste heat from hot flue gases to preheat $8,266 $3,000 - - $8,266
-
MMBtu
- - - -
08 2.3192: Use fossil fuel powered generator during peak demand periods $11,351 $10,000 $234
2,700
kWh
$11,548
-
kW-mo/yr
- $(-431.0)
-
MMBtu
- - -
09 2.1241: Reduce excessive boiler blowdown $5,234 $7,500 - - $5,234
-
MMBtu
- - - -
10 2.1233: Analyze flue gas for proper air/fuel ratio $2,121 - - - $2,121
-
MMBtu
- - - -
11 2.2163: Use minimum steam operating pressure $826 - - - $826
-
MMBtu
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $26,179 $97,386 $20,689
238,383
kWh
$5,964
-
kW-mo/yr
- - - - $(-474.0)
13 2.7135: Install occupancy sensors $6,486 $9,108 $5,139
59,212
kWh
$741
-
kW-mo/yr
- - - - $606
14 2.7142: Utilize higher efficiency lamps and/or ballasts $3,599 $9,362 $2,464
28,390
kWh
$710
-
kW-mo/yr
- - - - $425
TOTAL RECOMMENDED $121,634 $138,781 $66,840
770,139
kWh
$22,833
-
kW-mo/yr
$26,593
-
MMBtu
$(-431.0)
-
MMBtu
$2,172
-
Tgal
$4,078
-
Tgal
$(-451.0)
TOTAL IMPLEMENTED $57,572 $2,425 $38,314
441,454
kWh
$3,870
-
kW-mo/yr
$10,146
-
MMBtu
- $2,172
-
Tgal
$4,078
-
Tgal
$(-1,008.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs