Assessment Year | 2016 |
---|---|
Principal Product | Plastic Products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
95,000
ft2
|
Annual Production | 87,098,073
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $163,964 | 2,708,084 |
kWh
|
$0.061 | |
Electricity Demand | $79,647 | 8,652 |
kW-mo/yr
|
$9.21 | |
Electricity Fees | $2,212 | - |
|
- | |
Natural Gas | $47,827 | 8,559 |
MMBtu
|
$5.59 | |
Waste Disposal Costs | |||||
Water Usage | $7,044 | 2,584 |
Tgal
|
$2.73 | |
Water Disposal | $11,476 | 2,585 |
Tgal
|
$4.44 | |
TOTAL YEARLY COSTS | $312,170 | ||||
RECOMMENDED SAVINGS* | $49,136 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $191 | - |
$84
1,508
kWh
|
$107
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.2511: Insulate bare equipment | $15,783 | $5,438 |
$11,789
210,813
kWh
|
$3,994
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 3.4114: Replace city water with recycled water via cooling tower | $15,101 | $15,500 |
$5,839
104,409
kWh
|
- | - | - |
$3,525
-
Tgal
|
$5,737
-
Tgal
|
- | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,343 | $1,152 | - | - | - | - | - |
$3,343
-
Tgal
|
- | - | |
05 | 2.8112: Combine utility meters | $2,301 | - | - | - | $3,021 | - | - | - | - | $(-720.0) | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $260 | $17 |
$131
2,338
kWh
|
$129
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $319 | $1,000 |
$265
4,735
kWh
|
$262
-
kW-mo/yr
|
- | - | - | - | $(-208.0) | - | |
08 | 2.2136: Install / repair insulation on steam lines | $4,363 | $21,980 | - | - | - |
$4,363
-
MMBtu
|
- | - | - | - | |
09 | 2.7231: Use radiant heater for spot heating | $3,109 | $9,840 | - | - | - |
$3,109
-
MMBtu
|
- | - | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,366 | $23,200 |
$2,183
39,032
kWh
|
$2,158
-
kW-mo/yr
|
- | - | - | - | - | $25 | |
TOTAL RECOMMENDED | $49,136 | $78,127 |
$20,291
362,835
kWh
|
$6,650
-
kW-mo/yr
|
$3,021 |
$7,472
-
MMBtu
|
$3,525
-
Tgal
|
$9,080
-
Tgal
|
$(-208.0) | $(-695.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs