ITAC Assessment: UD0951
ITAC logo
ITAC Assessment: UD0951
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Metrology Machines
NAICS 334519: Other Measuring and Controlling Device Manufacturing
SIC 3829: Measuring and Controlling Devices, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 62
Plant Area 45,000
ft2
Annual Production 136,309
units
Production Hrs. Annual 2,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,167 1,115,440
kWh
Electricity Demand $17,444 2,700
kW-mo/yr
Natural Gas $8,114 1,229
MMBtu
TOTAL YEARLY COSTS $110,725
RECOMMENDED SAVINGS* $18,166 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,332

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7124: Make a practice of turning off lights when not needed $4,773 - $4,322
56,789
kWh
- $451 -
02 2.7135: Install occupancy sensors $3,278 $1,200 $2,753
36,173
kWh
- $525 -
03 3.2124: Convert to air assisted / airless paint guns $5,257 $700 $44
575
kWh
$113
-
kW-mo/yr
- $5,100
04 2.4239: Eliminate or reduce compressed air usage $780 $750 $780
10,255
kWh
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $746 $50 $667
8,760
kWh
$79
-
kW-mo/yr
- -
06 2.7241: Install outside air damper / economizer on hvac unit $3,332 $3,750 $3,332
43,776
kWh
- - -
TOTAL RECOMMENDED $18,166 $6,450 $11,898
156,328
kWh
$192
-
kW-mo/yr
$976 $5,100
TOTAL IMPLEMENTED $3,332 $3,750 $3,332
43,776
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs