Assessment Year | 2016 |
---|---|
Principal Product | Welded Wire Mesh Concrete Reinforcement |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $50 M to 100M |
# of Employees | 70 |
Plant Area |
133,100
ft2
|
Annual Production | 66,526
ton
|
Production Hrs. Annual | 7,920
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $447,691 | 7,246,800 |
kWh
|
$0.062 |
Electricity Demand | $150,244 | 16,908 |
kW-mo/yr
|
$8.89 |
Electricity Fees | $10,341 | - |
|
- |
Natural Gas | $26,202 | 3,530 |
MMBtu
|
$7.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,115 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $36,312 | $5,400 |
$29,602
495,923
kWh
|
$6,710
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,698 | $2,125 |
$1,384
23,186
kWh
|
$314
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,691 | $2,800 |
$1,449
24,270
kWh
|
$242
-
kW-mo/yr
|
- | - | |
04 | 2.3212: Optimize plant power factor | $9,976 | $4,120 | - | - | $9,976 | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $807 | $1,000 |
$658
11,019
kWh
|
$149
-
kW-mo/yr
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $66 | $500 |
$53
896
kWh
|
$13
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,996 | $57,770 |
$4,537
76,003
kWh
|
$2,238
-
kW-mo/yr
|
- | $221 | |
TOTAL RECOMMENDED | $57,546 | $73,715 |
$37,683
631,297
kWh
|
$9,666
-
kW-mo/yr
|
$9,976 | $221 | ||
TOTAL IMPLEMENTED | $44,115 | $64,170 |
$34,797
582,945
kWh
|
$9,097
-
kW-mo/yr
|
- | $221 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs