ITAC Assessment: UD0942
ITAC logo
ITAC Assessment: UD0942
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Temperature Control Equipment
NAICS 334519: Other Measuring and Controlling Device Manufacturing
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 94
Plant Area 75,000
ft2
Annual Production 2,000
units
Production Hrs. Annual 2,990
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,458 744,800
kWh
Electricity Demand $32,642 3,876
kW-mo/yr
Electricity Fees $523 -
Natural Gas $32,316 4,868
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,915 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $1,296 $50 - - $1,296 - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $245 $35 $181
2,621
kWh
$64
-
kW-mo/yr
- - - -
03 2.7135: Install occupancy sensors $2,012 $810 $1,248
18,049
kWh
$640
-
kW-mo/yr
- - $124 -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,967 $4,500 $1,254
18,139
kWh
$2,570
-
kW-mo/yr
- $(-857.0)
-
MMBtu
- -
05 2.7221: Lower temperature during the winter season and vice-versa $10,803 $9,350 - - - $10,803
-
MMBtu
- -
06 2.7314: Reduce ventilation air $7,691 $28,200 $(-1,960.0)
(-28,348)
kWh
$(-1,024.0)
-
kW-mo/yr
- $10,675
-
MMBtu
- -
07 2.7314: Reduce ventilation air $1,533 - $92
1,333
kWh
$25
-
kW-mo/yr
- $1,416
-
MMBtu
- -
08 3.5316: Contract a wood pallet recycling company $1,368 - - - - - - $1,368
TOTAL RECOMMENDED $27,915 $42,945 $815
11,794
kWh
$2,275
-
kW-mo/yr
$1,296 $22,037
-
MMBtu
$124 $1,368
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs