ITAC Assessment: UD0913
ITAC logo
ITAC Assessment: UD0913
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Plating-Zinc,Nickel,Zinc,Iron,Zinc
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 78
Plant Area 110,000
ft2
Annual Production 83,000
units
Production Hrs. Annual 6,120
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,511 2,539,897
kWh
Electricity Demand $34,535 7,284
kW-mo/yr
Natural Gas $121,058 19,619
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $494,350 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,061

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4325: Upgrade conveyors $528 $255 $528
8,738
kWh
- - - - -
02 2.7135: Install occupancy sensors $615 $570 $450
7,445
kWh
$69
-
kW-mo/yr
- - $96 -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $511 $1,275 $414
6,850
kWh
$97
-
kW-mo/yr
- - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,643 $8,500 $2,643
43,737
kWh
- - - - -
05 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa $1,623 $7,000 - - $1,623
-
MMBtu
- - -
06 2.1224: Replace boiler $19,697 $163,500 $3,240
49,505
kWh
$248
-
kW-mo/yr
$16,209
-
MMBtu
- - -
07 2.2414: Use waste heat from hot flue gases to preheat $4,485 $5,000 - - $4,485
-
MMBtu
- - -
08 2.2514: Cover open tanks $3,270 $6,780 - - $3,270
-
MMBtu
- - -
09 2.1123: Install automatic stack damper $2,665 - - - $2,665
-
MMBtu
- - -
10 3.4111: Use closed cycle process to minimize waste water production $414,555 $27,000 $(-933.0)
(-15,429)
kWh
$(-512.0)
-
kW-mo/yr
- - - $416,000
11 3.3123: Use decanting, flotation to remove contaminants $27,921 $55,000 $(-318.0)
(-5,246)
kWh
$(-326.0)
-
kW-mo/yr
- - $11,153 $17,412
12 3.4113: Treat and reuse rinse waters $15,837 $10,000 $(-851.0)
(-14,074)
kWh
$(-330.0)
-
kW-mo/yr
- $17,018
-
Tgal
- -
TOTAL RECOMMENDED $494,350 $284,880 $5,173
81,526
kWh
$(-754.0)
-
kW-mo/yr
$28,252
-
MMBtu
$17,018
-
Tgal
$11,249 $433,412
TOTAL IMPLEMENTED $7,061 $8,625 $864
14,295
kWh
$166
-
kW-mo/yr
$5,935
-
MMBtu
- $96 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs