| Assessment Year | 2014 | 
|---|---|
| Principal Product | Plating-Zinc,Nickel,Zinc,Iron,Zinc | 
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring | 
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring | 
| Sales Range | $10 Mto 50 M | 
| # of Employees | 78 | 
| Plant Area | 110,000 
ft2
 | 
| Annual Production | 83,000 
units
 | 
| Production Hrs. Annual | 6,120 
hrs
 | 
| Location (State) | Ohio | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $153,511 | 2,539,897 | 
kWh
 | $0.060 | 
| Electricity Demand | $34,535 | 7,284 | 
kW-mo/yr
 | $4.74 | 
| Natural Gas | $121,058 | 19,619 | 
MMBtu
 | $6.17 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $494,350 | See individual recommendations below*Non-energy impacts included in savings. | ||
| IMPLEMENTED SAVINGS* | $7,061 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | 
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4325: Upgrade conveyors | $528 | $255 | $528 8,738
                                 
kWh
 | - | - | - | - | - | |
| 02 | 2.7135: Install occupancy sensors | $615 | $570 | $450 7,445
                                 
kWh
 | $69 -
                                 
kW-mo/yr
 | - | - | $96 | - | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $511 | $1,275 | $414 6,850
                                 
kWh
 | $97 -
                                 
kW-mo/yr
 | - | - | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,643 | $8,500 | $2,643 43,737
                                 
kWh
 | - | - | - | - | - | |
| 05 | 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa | $1,623 | $7,000 | - | - | $1,623 -
                                 
MMBtu
 | - | - | - | |
| 06 | 2.1224: Replace boiler | $19,697 | $163,500 | $3,240 49,505
                                 
kWh
 | $248 -
                                 
kW-mo/yr
 | $16,209 -
                                 
MMBtu
 | - | - | - | |
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $4,485 | $5,000 | - | - | $4,485 -
                                 
MMBtu
 | - | - | - | |
| 08 | 2.2514: Cover open tanks | $3,270 | $6,780 | - | - | $3,270 -
                                 
MMBtu
 | - | - | - | |
| 09 | 2.1123: Install automatic stack damper | $2,665 | - | - | - | $2,665 -
                                 
MMBtu
 | - | - | - | |
| 10 | 3.4111: Use closed cycle process to minimize waste water production | $414,555 | $27,000 | $(-933.0) (-15,429)
                                 
kWh
 | $(-512.0) -
                                 
kW-mo/yr
 | - | - | - | $416,000 | |
| 11 | 3.3123: Use decanting, flotation to remove contaminants | $27,921 | $55,000 | $(-318.0) (-5,246)
                                 
kWh
 | $(-326.0) -
                                 
kW-mo/yr
 | - | - | $11,153 | $17,412 | |
| 12 | 3.4113: Treat and reuse rinse waters | $15,837 | $10,000 | $(-851.0) (-14,074)
                                 
kWh
 | $(-330.0) -
                                 
kW-mo/yr
 | - | $17,018 -
                                 
Tgal
 | - | - | |
| TOTAL RECOMMENDED | $494,350 | $284,880 | $5,173 81,526
                                 
kWh
 | $(-754.0) -
                                 
kW-mo/yr
 | $28,252 -
                                 
MMBtu
 | $17,018 -
                                 
Tgal
 | $11,249 | $433,412 | ||
| TOTAL IMPLEMENTED | $7,061 | $8,625 | $864 14,295
                                 
kWh
 | $166 -
                                 
kW-mo/yr
 | $5,935 -
                                 
MMBtu
 | - | $96 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs
             
             
             
            