ITAC Assessment: IA0345
ITAC logo
ITAC Assessment: IA0345
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product aluminum castings
NAICS 331523: Nonferrous Metal Die-Casting Foundries
SIC 3363: Aluminum Die-Castings
Sales Range $50
M
to 100
M
# of Employees 615
Plant Area 275,000
ft2
Annual Production 16,024
ton
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $728,399 24,350,000
kWh
Electricity Demand $453,152 42,161
kW-mo/yr
Natural Gas $1,078,435 271,499
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $175,511 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $125,392

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $27,434 $1,563 $19,841
644,674
kWh
$7,593
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $307 $215 $203
6,602
kWh
$104
-
kW-mo/yr
- - -
03 2.4239: Eliminate or reduce compressed air usage $3,283 $644 $1,981
64,320
kWh
$1,302
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,149 $7,098 $2,052
66,584
kWh
$1,097
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,195 $16,220 $4,335
140,672
kWh
$2,860
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $1,206 $2,062 $1,206
39,157
kWh
- - - -
07 2.4133: Use most efficient type of electric motors $1,085 $568 $704
22,852
kWh
$381
-
kW-mo/yr
- - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,305 $2,330 $2,230
69,500
kWh
$1,075
-
kW-mo/yr
- - -
09 2.4325: Upgrade conveyors $1,225 $2,145 $798
25,896
kWh
$427
-
kW-mo/yr
- - -
10 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $1,689 $1,828 $1,223
39,420
kWh
$466
-
kW-mo/yr
- - -
11 2.2514: Cover open tanks $12,884 $22,000 - - $12,884
-
MMBtu
- -
12 2.2414: Use waste heat from hot flue gases to preheat $21,035 $20,180 - - $21,035
-
MMBtu
- -
13 2.1133: Adjust burners for efficient operation $30,870 $10,000 - - $30,870
-
MMBtu
- -
14 4.424: Improve space comfort conditioning $1,584 $1,170 - - - $1,584 -
15 4.513: Re-arrange equipment layout to reduce labor costs $4,290 $1,035 - - - $4,290 -
16 4.513: Re-arrange equipment layout to reduce labor costs $4,290 $1,100 - - - $4,290 -
17 4.513: Re-arrange equipment layout to reduce labor costs $2,145 $399 - - - $2,145 -
18 4.423: Move product using mechanical means $11,717 $11,122 - - $3,995
-
MMBtu
$7,722 -
19 4.132: Purchase new equipment to reduce material use / cost $36,818 $85,000 - - $4,268
-
MMBtu
$8,250 $24,300
TOTAL RECOMMENDED $175,511 $186,679 $34,573
1,119,677
kWh
$15,305
-
kW-mo/yr
$73,052
-
MMBtu
$28,281 $24,300
TOTAL IMPLEMENTED $125,392 $89,387 $34,573
1,119,677
kWh
$15,305
-
kW-mo/yr
$64,789
-
MMBtu
$10,725 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs